Contractor Information
This page is maintained for the purpose of informing General Contractors of
upcoming and awarded work on the American Fork Pressurized Irrigation System.
|
PRIOR BIDS |
| Project-Lower Reservoir Transmission |
| Bid Date |
Mar. 4, 2008 |
| Low Bid |
$2,126,168.21 |
| Link to Bid Tab |
Lower Reservoir
Transmission |
| Awarded to: |
Terry Larsen Excavation |
| Project-Lower zone filter station |
| Bid Date |
Mar. 4, 2008 |
| Low Bid |
$307,060.00 |
| Link to Bid Tab |
Lower Zone Filter Station |
| Awarded to: |
K.W. Robinson Construction |
| Project-Schedule I Distribution |
| Bid Date |
April 1, 2008 |
| Low Bid |
$3,700,000.00 |
| Link to Bid Tab |
Schedule I Distribution |
| Awarded to: |
RAM Construction |
| Project-Schedule II Distribution |
| Bid Date |
April 29, 2008 |
| Low Bid |
$3,682,026.97 |
| Link to Bid Tab |
Schedule II Distribution |
| Awarded to: |
Skip Dunn and Sons Excavating |
| Project-Schedule V Distribution |
| Bid Date |
June 3, 2008 |
| Low Bid |
$2,725,825.00 |
| Link to Bid Tab |
Schedule V Distribution |
| Awarded to: |
VanCon Inc |
|
UPCOMING BIDS |
| Project-Lower Reservoir |
| Plans Available |
June 2008 at Franson Civil Engineers |
| Pre-Bid meeting |
June 24, 2008 |
| Bid Date |
July 1, 2008 |
| Description |
25 acre ft storage reservoir and appurtenances |
| Project-Schedule III Distribution |
| Plans Available |
Anticipated May, 2008 at Franson Civil Engineers |
| Pre-Bid meeting |
TBA |
| Bid Date |
Anticipated July 2008 |
| Description |
|
| Project-Schedule IV Distribution |
| Plans Available |
Anticipated May, 2008 at Franson Civil Engineers |
| Pre-Bid meeting |
TBA |
| Bid Date |
Anticipated July 2008 |
| Description |
|
| Project-Schedule VI Distribution |
| Plans Available |
Anticipated May, 2008 at Horrocks Engineers |
| Pre-Bid meeting |
July 8, 2008 |
| Bid Date |
July 15, 2008 |
| Description |
Approximately 49,000 feet of 36" to 4" distribution
system piping and appurtenances |
|
|